PROJECT NAME: MAVOKO WATER SUPPLY PROJECT
FINANCIER: BELGIUM/KENYA GOVERNMENTS
PROJECT COST: 2.5 BILLION
CONTRACTOR: ASPAC INTERNATIONAL
PROJECT OBJECTIVES: TO SUPPLY 12,000M3 PER DAY OF WATER TO MAVOKO & 5,000M3 TO SYOKIMAU.
PROJECT DURATION: 2 YEARS (Expected completion date Jan 2021)
TARGET POPULATION: 250,000 PEOPLE
PROJECT STATUS: Ongoing,
PROJECT COMPONENTS:
1) Nairobi-Syokimau Pipeline: Treated Water pipeline from General Motors to Syokimau,Construction of a 5,000 m3 reinforced concrete ground water reservoir, erection of a 3,000 m3 elevated storage tank to supply water to Syokimau area and its environs. Tanks 100% done, Nairobi line component 0% done ( delayed by commencement of the Nairobi express way project)
2 ) Nol-Turesh Pipeline: Rehabilitation of Nol-Turesh pipeline and Lukenya reservoir to supply water to Kyumvi and Daystar areas. 20% done
3) KMC DAM: Rehabilitation of KMC Dam and construction of a raw water mains to the new treatment plant. 20% done
4). EAPCC DAM:Rehabilitation of EAPCC Dam and construction of a raw water mains to the new treatment plant.85% done
5) New Water Treatment Plant:Construction of a modern 12,000 m3 per day treatment plant and a 5,000 m3 reinforced concrete ground water reservoir at Embakasi in Athiriver Town.85% done
PROJECT NAME: ATHI-RIVER SEWER LINES CONSTRUCTION AND UPGRADING PROJECT
FINANCIER: STATE DEPARTMENT OF HOUSING & URBAN DEVELOPMENT
PROJECT COST: 99 MILLION
PROJECT OBJECTIVES:
To construct & upgrade sewer systems within Athiriver town.Targeted areas are:-Njoguini,KMC-Madukani,Ngei II & Embakasi estates.
PROJECT SCOPE:
Construction of at least 9 km of sewer lines of diameters from 200 mm(8") to 400 mm(16") and associated manholes
PROJECT CONTRACTOR: EVER FORTUNES CO. LTD
PROJECT DURATION: 4 MONTHS (Expected completion date July 2020)
TARGET POPULATION: 18,000 PEOPLE
PROJECT STATUS: Ongoing. 95% complete
PROJECT NAME: LUKENYA TRUNK SEWER COMPLETION
PROJECT OBJECTIVES: To complete construction of the trunk sewerline to serve Daystar University and the larger Lukenya area
CONTRACT PERIOD: 16 Weeks
COMPLETION DATE: NOVEMBER 2020
CONTRACT SUM: KSH 15M
FINANCIER: MINISTRY OF HOUSING
PROJECT NAME: MAVOKO NHC SEWERAGE PROJECT
EXECUTING AGENCY: TANATHI WATER WORKS DEVELOPMENT AUTHORITY.
CONTRACTOR: VIMA CONTRACTORS
COMPLETION DATE: JAN 2021
PROJECT OBJECTIVES: To connect about 7,000 units at the Stoni Athi housing estate to sewer
PROJECT STATUS: 60 % done
PROJECT NAME: NAIROBI EXPRESSWAY WATER RELOCATION
EXECUTING AGENCY: ATHI WATER WORKS DEVELOPMENT AUTHORITY
CONTRACT PERIOD: 18 MONTHS
COMMENCED IN: APRIL 2020
CONTRACT SUM: 3BN
PROJECT OBJECTIVES: To relocate water services to pave way for the construction of the Nairobi express way project.